Al Dhafra Sports Club

Staff Accommodation ( G+2 ) 6Nos. Residential Buildings, Al Silaa

MEP WORKS (Completed)
Project Description MEP services were installed in 6 low-rise 3D panel buildings using thermal cutting to avoid stressing EPS- core panels.
Client M/S. Al Dhafra Sports & Cultural Club
Consultant M/S. Universal Building Engineering Consultants
Main Contractor M/S. Royal International Construction L.L.C
MEP Contractor M/S. Red Sea Eagle Electromechanical Contracting L.L.C
Scope of Works MEP Works For 88 Flats (16 # Studios, 8# 1bdr, 24 # 2bdr And 40# 3bdr)
Work Duration 11-Apr-18 - 10-Nov-19
Construction System Used 3D Panel
Build Up Area 6875 Sq.m
Peak MEP Manpower 52 Labours
Location Al Silaa-Abu Dhabi