Staff Accommodation ( G+2 ) 6Nos. Residential Buildings, Al Silaa
MEP WORKS (Completed)| Project Description | MEP services were installed in 6 low-rise 3D panel buildings using thermal cutting to avoid stressing EPS- core panels. |
|---|---|
| Client | M/S. Al Dhafra Sports & Cultural Club |
| Consultant | M/S. Universal Building Engineering Consultants |
| Main Contractor | M/S. Royal International Construction L.L.C |
| MEP Contractor | M/S. Red Sea Eagle Electromechanical Contracting L.L.C |
| Scope of Works | MEP Works For 88 Flats (16 # Studios, 8# 1bdr, 24 # 2bdr And 40# 3bdr) |
| Work Duration | 11-Apr-18 - 10-Nov-19 |
| Construction System Used | 3D Panel |
| Build Up Area | 6875 Sq.m |
| Peak MEP Manpower | 52 Labours |
| Location | Al Silaa-Abu Dhabi |