| Main Contractor | Force10 UAE LLC |
|---|---|
| MEP Contractor | M/S. Red Sea Eagle Electromechanical Contracting L.L.C |
| Scope of Works | ETS along with the Primary & Secondary UG Chilled Water Network |
| Key Challange | To ensure uninterrupted cooling for critical hospital operations, a redundant system was designed integrating district cooling as the primary source with an on-site chiller plant as a backup. The system automatically switches to the chiller in case of district cooling supply failure, maintaining continuous operation and compliance with healthcare facility requirements. |
| Work Duration | 12 Months |
| Location | Abu Dhabi |